Introduction to provisions Flood risk

Flood risk

0.8

Policies set out in the National Planning Policy Framework7 aim to avoid inappropriate development in areas at risk of flooding, including requiring new development to be flood resilient and resistant, as and where appropriate. Flood resistance is not currently a requirement in Schedule 1 of the Building Regulations 2010 (and amendments). However, when local considerations necessitate building in flood prone areas the buildings can be constructed to mitigate some effects of flooding such as:

a. elevated groundwater levels or flow of subsoil water across the site – this can be alleviated by the provision of adequate sub-soil drainage (see Section 3);
b. sewer flooding due to backflow or surcharging of sewers or drains – this can be addressed through the use of non-return valves and anti-flooding devices (see Section 3, paragraph 3.6);

7 National Planning Policy Framework, Communities and Local Government, March 2012.

c. intrusion of groundwater through floors – this can be addressed through the use of water resistant construction (see Section 4, paragraphs 4.7 to 4.12);
d. entry of water into floor voids – provision to inspect and clear out sub-floor voids can be considered (see Section 4, paragraph 4.20).

Further information on flood resistant and resilient construction can be found in the publication Improving the flood performance of new buildings – Flood resilient construction8.