Section 1: Clearance or treatment of unsuitable material Site investigation

Site investigation

1.1

The preparation of the site will depend on the findings of the site investigation. The site investigation is relevant to Sections 1, 2 and 3 of this Approved Document and also to the requirements of Approved Document A with respect to foundations. The site investigation should consist of a number of well-defined stages:

a. Planning stage. Clear objectives should be set for the investigation, including the scope and requirements, which enable the investigation to be planned and carried out efficiently and provide the required information;
b. Desk study. A review of the historical, geological and environmental information about the site is essential;
c. Site reconnaissance or walkover survey. This stage of the investigation facilitates the identification of actual and potential physical hazards and the design of the main investigation;
d. Main investigation and reporting. This will usually include intrusive and non-intrusive sampling and testing to provide soil parameters for design and construction. The main investigation should be preceded by (b) and (c) above.

1.2

The extent and level of investigation need to be tailored to the type of development and the previous use of land. Typically the site investigation should include susceptibility to groundwater levels and flow, underlying geology, and ground and hydro-geological properties. A geotechnical site investigation should identify physical hazards for site development, determine an appropriate design and provide soil parameters for design and construction. BS EN 1997-2:2007: Eurocode 7: Geotechnical design with its UK National Annex14 supported by BS 5930:1999+A2:201036 provide comprehensive guidance on site investigation. Guidance on site investigation for low-rise buildings is given in six BRE Digests covering procurement15, desk studies16, the walk-over survey17, trial pits18, soil description19 and direct investigation20. Reference should also be made to BS 8103-1:201121.

1.3

Where the site is potentially affected by contaminants, a combined geotechnical and geo-environmental investigation should be considered. Guidance on assessing and remediating sites affected by contaminants is given in Section 2: Resistance to contaminants.