Section 5: Walls Joint between doors and windows
Joint between doors and windows
5.29
The joint between walls and door and window frames should:
5.30
Damp-proof courses should be provided to direct moisture towards the outside:
5.31
In some cases the width of the cavity due to thermal insulation and the 50mm clearance for drainage may be such that the window frame is not wide enough to completely cover the cavity closer. The reveal may need to be lined with plasterboard, dry lining, a support system or a thermal backing board. Direct plastering of the internal reveal should only be used with a backing of expanded metal lathing or similar.
5.32
In areas of the country in driving rain exposure zone 4 checked rebates should be used in all window and door reveals. The frame should be set back behind the outer leaf of masonry, which should overlap it as shown in Diagram 13. Alternatively an insulated finned cavity closer may be used.
Diagram 13 Window reveals for use in areas of severe or very severe exposure to driving rain (see paragraph 5.32)