Regulation 40B: Providing information
Regulation 40B: Providing information
This section deals with the requirements of regulation 40B of the Building Regulations 2010.
Regulation
Information about overheating
40B. (1) This regulation applies to building work in respect of a building where Part O of Schedule 1 applies.
(2) The person carrying out the work must, not later than five days after the work has been completed, give sufficient information to the owner about the provision made in accordance with Part O so that the systems in place further to Part O can be operated in such a manner as to protect against overheating.
Intention
When a new residential building is erected, information about the building must be given to the owner of the building to allow them to use the overheating mitigation strategy effectively.
In the Secretary of State’s view, regulation 40B is met by providing information in accordance with Section 4.