Application 1.19

1.19

Where a ducting system is being used for installation of gigabit-ready physical infrastructure to a network distribution point, installation is likely to be to a point where the development site meets the public highway.

NOTE: Where a next fastest broadband connection or no connection to a public electronic communications network can be provided within the cost cap (see paragraphs 2.13 to 2.23), new dwellings must still be erected with gigabit-ready physical infrastructure installed to be ready to support a connection to a gigabit-capable public electronic communications network in the future. In these cases, the gigabit-ready physical infrastructure is required to have sufficient capacity and dimensions to install and host a gigabit-capable public electronic communications network connection for each dwelling.