Application 1.7
1.7
Where a developer seeks to rely on the building being in an ‘isolated area’ as a reason to exempt new dwellings from requirement RA1, the developer must provide evidence in support of the exemption. This should include an explanation of how new dwellings are in an area that is isolated from a relevant connection, that the cost of providing a USO-standard public electronic communications network connection exceeds the cost cap and why the prospect of a connection to a relevant network in the isolated area is considered too remote to justify equipping the building with the relevant gigabit-ready physical infrastructure. The application of this exemption will vary in different circumstances.
NOTE: This evidence can be provided with the information submitted with the application for Building Regulations approval. The connectivity plan at Appendix B, which sets out a template for developers, can be used to provide such evidence and information.