Suspended timber ground floors (moisture from the ground) Alternative approach
Alternative approach
4.16
The requirement can also be met (see paragraph 4.14 above) by following the relevant recommendations of Clause 11 of BS CP 102:197394.
The requirement can also be met (see paragraph 4.14 above) by following the relevant recommendations of Clause 11 of BS CP 102:197394.