Cost cap 2.23

2.23

The following are excluded from costs assessed against the cost cap.

a. The cost to the developer of installing gigabit-ready physical infrastructure in relation to each dwelling erected, including infrastructure in common areas in a building containing more than one dwelling, in accordance with requirement RA1.
b. Administrative costs of the developer, including costs of submitting the connectivity plan and building control body fees as applicable.
c. The cost to an end-user (as defined in section 151(1) of the Communications Act 2003) of the provision of a public electronic communications service.

NOTE: Any financial contribution from the network operator should be deducted from the cost of providing the relevant connection.