Section 2: Requirement RA2 – connection to gigabit-capable network
Section 2: Requirement RA2 – connection to gigabit-capable network
This section deals with requirement RA2 from Part R of Schedule 1 and regulation 44ZC of the Building Regulations 2010.
Requirement
| Requirement | Limits on application |
|---|---|
Part R Infrastructure for electronic communications Connection to gigabit-capable network RA2 Each dwelling must in addition be provided with a connection to a gigabit-capable public electronic communications network. | Requirements RA1 and RA2 apply to the erection of a dwelling or of a building that contains one or more dwellings. |
Regulation
Cases in which paragraph RA2 of Schedule 1 is modified or excluded
44ZC. (1) The requirement in paragraph RA2 of Schedule 1 has effect subject to paragraphs (2) to (4).
Intention
2.1
In the Secretary of State’s view, requirement RA2 will be met by installing a relevant connection from a network distribution point to a network termination point at each new dwelling erected on a development site. Requirement RA2 requires developers to install a functioning connection to a gigabit-capable public electronic communications network but does not require developers to secure the provision of a public electronic communications service with an internet service provider.
2.2
Developers should work with network operators to provide a gigabit-capable public electronic communications network connection for each new dwelling erected unless the cost exceeds the cost cap of £2000 per dwelling or the network operator declines to provide a connection.
2.3
Where a gigabit-capable public electronic communications network connection is not being installed because a connection is not offered within the £2000 cost cap, developers should work with network operators to provide the next fastest broadband connection which can be installed without exceeding the £2000 cost cap.
NOTE: Developers may decide to install, for each new dwelling erected, connections to more than one gigabit-capable public electronic communications network. This can be done within one system of gigabit-ready physical infrastructure with capacity to host more than one type of connection. While developers may secure a gigabit-capable public electronic communications network connection from the first suitable network operator with which they engage, they may approach multiple network operators to secure multiple connections on a voluntary basis.
2.4
The connection to a gigabit-capable public electronic communications network can be provided in the following ways.
2.5
The technologies that can currently provide a connection to a gigabit-capable public electronic communications network are set out in the most recent Ofcom Connected Nations report. The 2021 report sets out that relevant technologies include fibre to the premises (‘full fibre’, meaning optical fibre all the way to the dwelling) and other cable types, such as Data Over Cable Service Interface Specification (DOCSIS 3.1) or Fixed Wireless Access (depending on the specific deployment, available capacity at the site, and the number and location of users).
2.6
At least one network termination point should be provided in a suitable position at each new dwelling erected.
NOTE: The network termination point is usually inside the dwelling in an open area. Developers should consider the optimal location of the network termination point and the gigabit-ready physical infrastructure extending to it. In some dwellings, wireless coverage may not extend from the network termination point to all rooms in the dwelling. Some developers may decide to include wired distribution within the dwelling at the time of construction to ensure good connectivity for residents. For further advice see the NHBC Foundation’s NF67 The Connected Home: Designing and Building Technology into Today’s New Homes [2016].
2.7
A fixed electrical supply for the network termination point and associated distribution equipment should be provided at the network termination point.
2.8
The fixed electrical supply should comply with Part P in Schedule 1 to the Building Regulations (Electrical safety – dwellings). For new dwellings, the services and controls for the network termination point and fixed electrical supply, including socket outlets and switches, should be in a position which is easy to reach in accordance with the services and controls guidance supporting Part M in Schedule 1 to the Building Regulations (Access to and use of buildings).
Application
2.9
Requirement RA2 for a connection to a gigabit-capable public electronic communications network applies to the erection of a new dwelling or of a building that contains one or more dwellings.
2.10
A new dwelling may be a dwelling-house or a flat in a building that contains one or more dwellings.
2.11
New dwellings include the following:
2.12
Requirement RA2 does not apply to the following types of dwellings, buildings or building work.
Modification and exemptions
2.13
Requirement RA2 does not apply if the cost of providing either a gigabit-capable public electronic communications network connection or each of the next fastest broadband connections would exceed the cost cap.
2.14
The cost cap for each dwelling is £2000 (see paragraphs 2.21 to 2.23).
2.15
The developer should contact at least two suitable network operators, and provide evidence to demonstrate that an exemption applies where the offers from the suitable network operators exceed the cost cap. Where the developer has not invited two suitable network operators to provide such a connection, they will be treated as being able to secure the provision of that connection within the cost cap.
2.16
Evidence that the chosen network operators are suitable should be provided. Developers will need to ensure the network operator is suitable for the purposes of requirement RA2. In determining which network operator is most likely to be able to provide the connection, the developer is encouraged to take into account factors such as the following:
2.17
Where the cost of connection to a gigabit-capable public electronic communications network exceeds the cost cap, connection to the next fastest broadband connection should be provided, in the following order of priority.
2.18
As the requirements are technologically neutral, alternative technologies (such as fixed wireless or satellite technologies) should be considered where performance requirements can be met, before consideration is given to installing a slower form of connection.
2.19
Requirement RA1 to install gigabit-ready physical infrastructure at each individual dwelling still applies when new dwellings are erected without a connection or regardless of the speed of the connection installed at the point of construction.
2.20
Requirement RA2 does not prescribe the method for developers to obtain offers and other relevant information from network operators, although there is a prescribed time limit of 30 working days for receipt of such offers. Developers may choose to request an offer from suitable network operators to provide a connection to all of the following:
If the cost of connection to a gigabit-capable public electronic communications network exceeds the cost cap, developers can consider the network operators’ quotes for the slower connections.
Cost cap
2.21
The cost cap for the developer is £2000 for each new dwelling erected, after any financial contribution from the network operator has been deducted.
2.22
The following should be included in costs assessed against the cost cap.
NOTE: Costs may include direct costs to the developer and costs to the developer of subcontracting to network operators.
2.23
The following are excluded from costs assessed against the cost cap.
NOTE: Any financial contribution from the network operator should be deducted from the cost of providing the relevant connection.