Intention 2.3
2.3
Where a gigabit-capable public electronic communications network connection is not being installed because a connection is not offered within the £2000 cost cap, developers should work with network operators to provide the next fastest broadband connection which can be installed without exceeding the £2000 cost cap.
NOTE: Developers may decide to install, for each new dwelling erected, connections to more than one gigabit-capable public electronic communications network. This can be done within one system of gigabit-ready physical infrastructure with capacity to host more than one type of connection. While developers may secure a gigabit-capable public electronic communications network connection from the first suitable network operator with which they engage, they may approach multiple network operators to secure multiple connections on a voluntary basis.