Scope of the connectivity plan 3.4
3.4
If an exemption is to be relied on for requirement RA1 or requirement RA2, Part B of the connectivity plan should also be completed and supporting evidence should be included with the connectivity plan when it is submitted. The following information should be provided.
a. Evidence from at least two suitable network operators that demonstrates one of the following.
i. The cost of providing a connection to a gigabit-capable public electronic communications network exceeds the cost cap, with accompanying quotes provided by the suitable network operators.
ii. The suitable network operators refused to provide a gigabit-capable public electronic communications network connection, and evidence demonstrating the reason for this refusal.
iii. The suitable network operators have not responded within the 30 working day period.
b. Also provide evidence in support of any exemption relied upon for requirement RA1 to provide gigabit-ready physical infrastructure.