Section 2: Requirement RA2 – connection to gigabit-capable network Modification and exemptions

Modification and exemptions

2.13

Requirement RA2 does not apply if the cost of providing either a gigabit-capable public electronic communications network connection or each of the next fastest broadband connections would exceed the cost cap.

2.14

The cost cap for each dwelling is £2000 (see paragraphs 2.21 to 2.23).

2.15

The developer should contact at least two suitable network operators, and provide evidence to demonstrate that an exemption applies where the offers from the suitable network operators exceed the cost cap. Where the developer has not invited two suitable network operators to provide such a connection, they will be treated as being able to secure the provision of that connection within the cost cap.

2.16

Evidence that the chosen network operators are suitable should be provided. Developers will need to ensure the network operator is suitable for the purposes of requirement RA2. In determining which network operator is most likely to be able to provide the connection, the developer is encouraged to take into account factors such as the following:

a. the location of the development site
b. the ability of a network operator to provide a suitable connection in the locality of the development site
c. the variety of network operators in the locality of the development site
d. network operators’ deployment plans in the locality of the development site
e. other network operators, not necessarily in the locality of the development site, that might deploy there in the future.

2.17

Where the cost of connection to a gigabit-capable public electronic communications network exceeds the cost cap, connection to the next fastest broadband connection should be provided, in the following order of priority.

a. Connection to a high-speed electronic communications network.
b. Connection to a USO-standard public electronic communications network.

2.18

As the requirements are technologically neutral, alternative technologies (such as fixed wireless or satellite technologies) should be considered where performance requirements can be met, before consideration is given to installing a slower form of connection.

2.19

Requirement RA1 to install gigabit-ready physical infrastructure at each individual dwelling still applies when new dwellings are erected without a connection or regardless of the speed of the connection installed at the point of construction.

2.20

Requirement RA2 does not prescribe the method for developers to obtain offers and other relevant information from network operators, although there is a prescribed time limit of 30 working days for receipt of such offers. Developers may choose to request an offer from suitable network operators to provide a connection to all of the following:

a. a gigabit-capable public electronic communications network
b. a high-speed electronic communications network
c. a USO-standard public electronic communications network.

If the cost of connection to a gigabit-capable public electronic communications network exceeds the cost cap, developers can consider the network operators’ quotes for the slower connections.