Impervious cladding systems for walls Technical solution
Technical solution
5.23
Cladding may be:
5.24
Dry joints between cladding units should be designed so that precipitation will not pass through them, or the cladding should be designed so that precipitation which enters the joints will be directed towards the exposed face without it penetrating beyond the back of the cladding. Note: Whether dry joints are suitable will depend on the design of the joint or the design of the cladding and the severity of the exposure to wind and rain.
5.25
Each sheet, tile and section of cladding should be securely fixed. Guidance as to appropriate fixing methods is given in BS 8000-6:1990117. Particular care should be taken with detailing and workmanship at the junctions between cladding and window and door openings as they are vulnerable to moisture ingress.
5.26
Insulation can be incorporated into the construction provided it is either protected from moisture or unaffected by it.
5.27
Where cladding is supported by timber components or is on the façade of a timber framed building, the space between the cladding and the building should be ventilated to ensure rapid drying of any water that penetrates the cladding.
113 BRE Report BR 262 Thermal insulation: avoiding risks, 2002.
114 BRE Report 352 BRE Building elements: Walls, windows and doors, 2002.
115 BRE Report BR 292 Cracking in buildings, 1995.
116 BS 5628-3:2001 Code of practice for use of masonry. Materials and components, design and workmanship.
117 BS 8000-6:1990 Workmanship on building sites. Code of practice for slating and tiling of roofs and claddings.