Division of corridors 2.27

2.27

For buildings other than dwellings (purpose groups 2 to 7): if a cavity exists above the enclosures to a corridor as described above (because the enclosures are not carried to full storey height or the underside of the roof covering at the top storey), the potential for smoke to bypass the enclosure should be restricted by one of the following methods.

a. Method 1 – Fitting cavity barriers on the line of the enclosure(s) to and across the corridor (Diagram 2.9).
b. Method 2 – Dividing the storey using fire resisting construction that passes through the line of the division of the corridor (Diagram 2.9). Any cavity above this division should be fitted with cavity barriers on the line of division of the storey and the corridor.
c. Method 3 – Enclosing the cavity on the lower side by a fire resisting ceiling that extends throughout the building, compartment or separated part.

Any door that could provide a path for smoke to bypass the division should be fitted with a selfclosing device (but need not necessarily be fire resisting).